Notifications
You must be signed in to change notification settings - Fork 0
Expand file tree
/
Copy pathDetailed.plan
More file actions
212 lines (177 loc) · 4.31 KB
/
Copy pathDetailed.plan
File metadata and controls
212 lines (177 loc) · 4.31 KB
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
project: Downtown Corridor Improvement Project
start: 2026-01-05
finish: 2026-11-30
task 1 Project Management
task 1.1 Notice to Proceed 0d
task 1.2 Project Kickoff 0d
depends 1.1
task 1.3 Project Management Plan 10d
depends 1.2
task 1.4 Monthly Progress Reporting 240d
depends 1.2
task 2 Survey and Existing Conditions
task 2.1 Topographic Survey 15d
depends 1.2
task 2.2 Utility Research and Locating 15d
depends 1.2
task 2.3 Existing Conditions Report 5d
depends 2.1
depends 2.2
task 3 Design
task 3.1 Preliminary Design
task 3.1.1 Design Criteria 5d
depends 2.3
task 3.1.2 Roadway and Drainage Concept 20d
depends 3.1.1
task 3.1.3 Preliminary Design Review 0d
depends 3.1.2
task 3.2 Final Design
task 3.2.1 Roadway and Drainage Plans 25d
depends 3.1.3
task 3.2.2 Utility Plans 20d
depends 3.1.3
task 3.2.3 Specifications and Cost Estimate 15d
depends 3.2.1
depends 3.2.2
task 3.2.4 Final Design Review 0d
depends 3.2.3
task 4 Public and Agency Coordination
task 4.1 Public Open House 0d
depends 3.1.3
task 4.2 Public Comment Period 15d
depends 4.1
task 4.3 Agency Review 20d
depends 3.1.3
task 4.4 Agency Approval 0d
depends 4.3
task 4.5 Utility Coordination Meeting 0d
depends 3.2.2
task 4.6 Utility Agreements and Clearances 20d
depends 4.5
task 5 Permitting and Bid
task 5.1 Permit Application 10d
depends 3.2.4
task 5.2 Permit Agency Review 45d
depends 5.1
task 5.3 Permit Issuance 0d
depends 5.2
task 5.4 Bid Documents 15d
depends 3.2.4
task 5.5 Bid Advertisement 0d
depends 5.3
depends 5.4
task 5.6 Contractor Bid Period 21d
depends 5.5
task 5.7 Contract Award 5d
depends 5.6
task 5.8 Notice to Proceed for Construction 0d
depends 5.3
depends 5.7
task 6 Construction
task 6.1 Construction Mobilization
task 6.1.1 Preconstruction Meeting 0d
depends 5.8
task 6.1.2 Mobilization and Traffic Control 15d
depends 6.1.1
task 6.2 Roadway and Site Construction
task 6.2.1 Removal and Demolition 20d
depends 6.1.2
task 6.2.2 Utility Relocation 30d
depends 6.1.2
task 6.2.3 Subgrade and Aggregate Base 25d
depends 6.2.1
depends 6.2.2
depends 4.6
task 6.2.4 Curb and Gutter 25d
depends 6.2.3
task 6.2.5 Asphalt Paving 15d
depends 6.2.4
task 6.2.6 Sidewalk and ADA Ramps 25d
depends 6.2.3
task 6.2.7 Streetscape and Lighting 25d
depends 6.2.1
task 6.2.8 Substantial Completion 0d
depends 6.2.5
depends 6.2.6
depends 6.2.7
task 7 Closeout
task 7.1 Record Drawings 20d
depends 6.2.8
task 7.2 Operations and Maintenance Manuals 15d
depends 6.2.8
task 7.3 Project Management Closeout 5d
depends 6.2.8
task 7.4 Final Payment Package 10d
depends 7.1
depends 7.2
depends 7.3
task 7.5 Final Acceptance 0d
depends 7.4
task 7.6 Project Complete 0d
depends 7.5
;Tracking:
2026-01-05
1.1 start
1.1 complete
1.2 start
1.2 complete
2026-01-06 1.3 start
2026-01-16 1.3 complete
2026-01-06 1.4 start
2026-02-27 1.4 progress 30%
2026-04-30 1.4 progress 55%
2026-06-30 1.4 progress 75%
2026-08-31 1.4 progress 90%
2026-01-07 2.1 start
2026-01-21 2.1 complete
2026-01-07 2.2 start
2026-01-21 2.2 complete
2026-01-22 2.3 start
2026-01-26 2.3 complete
2026-01-27 3.1.1 start
2026-01-31 3.1.1 complete
2026-02-02 3.1.2 start
2026-02-21 3.1.2 complete
2026-02-22 3.1.3 start
2026-02-22 3.1.3 complete
2026-02-23 3.2.1 start
2026-03-19 3.2.1 complete
2026-02-23 3.2.2 start
2026-03-14 3.2.2 complete
2026-02-23 4.1 start
2026-02-23 4.1 complete
2026-02-24 4.2 start
2026-03-10 4.2 complete
2026-02-24 4.3 start
2026-03-16 4.3 complete
2026-03-17 4.4 start
2026-03-17 4.4 complete
2026-03-20 3.2.3 start
2026-04-03 3.2.3 complete
2026-04-06 3.2.4 start
2026-04-06 3.2.4 complete
2026-04-07 5.1 start
2026-04-16 5.1 complete
2026-04-07 5.4 start
2026-04-21 5.4 complete
2026-04-17 5.2 start
2026-05-20 5.2 progress 70%
2026-05-30 5.2 complete
2026-05-31 5.3 start
2026-05-31 5.3 complete
2026-06-01 5.5 start
2026-06-01 5.5 complete
2026-06-02 5.6 start
2026-06-22 5.6 complete
2026-06-23 5.7 start
2026-06-27 5.7 complete
2026-06-28 5.8 start
2026-06-28 5.8 complete
2026-06-29 6.1.1 start
2026-06-29 6.1.1 complete
2026-06-30 6.1.2 start
2026-07-14 6.1.2 complete
2026-07-15 6.2.1 start
2026-08-20 6.2.1 progress 80%
2026-07-15 6.2.2 start
2026-08-25 6.2.2 progress 85%