MVP Requirement:
Demonstrate future scenarios with
- two management scenarios (e.g. baseline + stacked)
- two emissions pathway scenarios
- two climate models
(that is eight simulations)
Use 45km grid because that is similar to the 0.5 degree ERA5 grid we are currently using.
What this means operationally output is in PEcAn std. format NetCDF
Steps
prerequisites
- Determine what source (caladapt wrf?)
- flesh out subtasks, including but not limited to:
- implementing PEcAn functions is not MVP. Coercing to PEcAn standard for use in scenario based projections is MVP
MVP Requirement:
Demonstrate future scenarios with
(that is eight simulations)
Use 45km grid because that is similar to the 0.5 degree ERA5 grid we are currently using.
What this means operationally output is in PEcAn std. format NetCDF
Steps
prerequisites