Scenario
I manufacture 7 different finished products.
All 7 products:
-Pass through the same 4 operations
-Use the same machines
-Follow the same sequence
-Have similar processing logic
The machines and routing logic are identical for all 7 products.
My Question
To configure this properly in frepple:
-Do I need to create a separate routing (parent operation) for each product?
-And then duplicate the same 4 suboperations under each parent?
-Or is there a way to reuse the same routing across multiple products?
In other words:
If the operations and machines are identical, what is the recommended modeling approach?
Create:
7 parent routing operations (one per product)
Each with the same 4 suboperations duplicated
I want to:
-Avoid unnecessary duplication
-Keep the model clean and scalable
-Still maintain accurate capacity planning
Any clarification on the recommended structure would be appreciated.
reacted with thumbs up emoji reacted with thumbs down emoji reacted with laugh emoji reacted with hooray emoji reacted with confused emoji reacted with heart emoji reacted with rocket emoji reacted with eyes emoji
Uh oh!
There was an error while loading. Please reload this page.
-
Here is a clear and professional draft you can post:
Multiple Products Sharing the Same Operations – Best Modeling Approach?
Hi,
I have a modeling question regarding multiple products that follow the same production process.
Scenario
I manufacture 7 different finished products.
All 7 products:
-Pass through the same 4 operations
-Use the same machines
-Follow the same sequence
-Have similar processing logic
Example process:
Operation 1 → Operation 2 → Operation 3 → Operation 4
The machines and routing logic are identical for all 7 products.
My Question
To configure this properly in frepple:
-Do I need to create a separate routing (parent operation) for each product?
-And then duplicate the same 4 suboperations under each parent?
-Or is there a way to reuse the same routing across multiple products?
In other words:
If the operations and machines are identical, what is the recommended modeling approach?
Create:
7 parent routing operations (one per product)
Each with the same 4 suboperations duplicated
I want to:
-Avoid unnecessary duplication
-Keep the model clean and scalable
-Still maintain accurate capacity planning
Any clarification on the recommended structure would be appreciated.