406 changes: 207 additions & 199 deletions docs/architecture/FORGE_V1_IMPLEMENTATION_DAG.md

Large diffs are not rendered by default.

Original file line number Diff line number Diff line change
@@ -0,0 +1,185 @@
# Living Mission Graph and cross-repository Engineering Action DAG

**Status:** target Forge architecture; canonical when merged. Implementation and qualification remain separately governed.

## Purpose

An approved Mission is the stable human-governed boundary. Forge owns the dynamic engineering plan inside that boundary. It must be able to derive the first Engineering Action, reconcile real execution evidence, change the remaining plan, derive additional Actions, and stop only when Mission completion is proven by evidence.

The active plan is the **Living Mission Graph**: a mutable planning graph of current Intents and not-yet-completed Engineering Actions. It is not the Roadmap DAG and it is not an EP scheduling queue.

```text
approved Mission
-> Forge plan / Living Mission Graph
-> materialized Engineering Action
-> EP execution
-> terminal receipt / repository evidence / findings
-> Forge reconcile + Project Context refresh
-> Mission completion evaluation
-> complete, or
-> replan / add, split, supersede, reorder or retire remaining work
-> next eligible Action(s)
```

`OWNER_DEFINES_MISSION_BOUNDARY = TRUE`
`FORGE_DEFINES_AND_REDEFINES_ACTION_PLAN = TRUE`
`EP_EXECUTES_ACTIONS = TRUE`
`EVIDENCE_DRIVES_REPLAN = TRUE`

## Dynamic inner Mission loop

Forge must not require the owner to predeclare Action A, B, C or relay execution results between them. A Mission can begin with only its objective, constraints and success criteria. Forge may forecast likely work, but forecast work is not immutable backlog.

After every material terminal result Forge:

1. verifies and reconciles the exact EP result;
2. refreshes repository/project truth and relevant quality findings;
3. evaluates the Mission success criteria and unresolved constraints;
4. revises the Living Mission Graph when evidence changes the required work;
5. materializes only bounded eligible Actions;
6. continues without another owner message while remaining inside the approved Mission boundary.

A result may therefore cause `A -> B -> B2 -> C`, even when `B2` was not known before B executed. A forecast successor may also disappear when the new evidence proves it unnecessary.

A change to the Mission objective, approved scope, constitutional constraints, destructive authority or security authority remains a governance change rather than ordinary replanning.

## Engineering Action target and immutability

The normal V1 planning unit is **one Engineering Action targeting one repository**. The Action snapshot carries the repository identity and bounded write scope required by EP admission. Cross-repository outcomes are normally decomposed into separate Actions connected by dependency edges rather than one opaque multi-repository prompt.

Conceptually an Action snapshot must be able to carry:

```text
EngineeringAction
id / revision
mission_id / mission_revision
intent_id / intent_revision
target_repository_id
write_scope
objective
acceptance / expected evidence
depends_on[]
dependency evidence requirements
```

A planned node may change before materialization. Once an Action is materialized for submission, its execution identity, target, objective, dependency snapshot and expected evidence are immutable. New evidence creates a new/revised successor Action or graph edge; Forge never rewrites historical execution identity.

`UNMATERIALIZED_PLAN_MAY_CHANGE = TRUE`
`MATERIALIZED_ACTION_IS_IMMUTABLE = TRUE`

## Hard dependencies

`depends_on` means a **hard logical execution dependency**: the successor is not eligible for dispatch until the required predecessor completion evidence exists and satisfies the dependency requirement.

Hard dependencies are planned by Forge. EP may durably persist and enforce the supplied dependency snapshot, but EP must not invent product or engineering dependencies.

A hard edge may exist within one repository or across repositories. Cross-repository edges are first-class because product delivery often spans independently owned repositories.

Do not overload `depends_on` with scheduling preference, forecast likelihood, shared-repository exclusion or Agent capacity. Those are separate concerns.

## Logical dependency, resource exclusion and capacity are separate

Three independent mechanisms determine whether work can run now:

1. **Logical dependency — Forge-owned plan.** Example: final installer manifest depends on published qualified EP artifacts.
2. **Repository/resource exclusion — EP-owned execution safety.** Independent Actions may still serialize when they require the same exclusive repository lease or other execution resource.
3. **Agent/provider capacity — EP-owned admission/placement.** Independent, lock-compatible Actions may still wait when no qualified execution capacity is available.

Consequently two Actions in different repositories with no dependency should be eligible for parallel execution when EP has safe capacity. Different repositories do not imply independence, and the same project does not imply serialization.

## Evidence-gated cross-repository unlock

A dependency can require a concrete producer artifact rather than merely a predecessor status flag. The predecessor Action DoD defines the evidence required to unlock the successor.

Example Mission: **make Engineering Platform Execution Agents production-ready and installable through Forge Platform**.

```text
EP-A1 Agent contract
|\
| +--> EP-A2 Agent runtime -------------------+
| |
+----> EP-A3 Server <-> Agent protocol ------+--> EP-A4 qualification/package
|
v
EP-A5 publish qualified artifacts
server wheel + agent wheel
source revision + artifact SHA-256
|
+-------------------------+
|
FP-A1 installer Agent role/model --> FP-A2 installer support -----------------+--> FP-A3 final component manifest
|
v
FP-A4 installer qualification
```

`EP-A2/EP-A3` work and `FP-A1/FP-A2` work can advance in parallel when their own dependencies and EP execution resources permit. `FP-A3` has hard dependencies on both the installer implementation and `EP-A5`. It cannot finalize the component manifest until qualified artifacts actually exist.

The artifact-producing predecessor should expose at least the installable artifact identity, artifact digest, source revision and relevant qualification/provenance references. A source commit alone is not sufficient proof of the bytes the installer will install.

## Dispatch and EP enforcement boundary

Forge determines which Actions exist, their repository target and their `depends_on` graph. Forge should normally submit only currently eligible Actions. The immutable submission also carries enough predecessor identity/evidence requirements for EP to fail closed if an ineligible successor is presented.

EP owns admission, repository leases, execution capacity, run state, validation/review/repair and terminal evidence. A dependency check by EP enforces the producer-supplied plan; it does not transfer planning authority to EP.

```text
Forge Living Mission Graph
-> eligible Action snapshot + dependency requirements
-> EP admission
hard predecessor evidence satisfied?
repository/resource lease available?
qualified Agent/provider capacity available?
-> dispatch or durable wait
```

## Parallel release from one Mission

The target Runtime may release more than one eligible Action from the same Mission. It should select the maximal safe set allowed by the Living Mission Graph and submit them independently. EP remains free to serialize or delay them for execution-resource reasons.

The current Bootstrap Mission Scheduler's single in-flight Action rule is a bootstrap implementation limit, not a target invariant. The current runner-wide repository target is likewise a bootstrap limit; target architecture requires repository identity at the Action/submission boundary.

## Mission completion

Mission completion is not defined as “all Actions from the initial plan are COMPLETE”. The initial plan is provisional.

After reconciliation Forge must prove that the approved Mission success criteria are satisfied from current evidence and that no unresolved required work remains inside the Mission boundary. Only then may it mark the Mission complete.

A complete set of initially forecast Actions is insufficient if evidence exposes new required work. Conversely, Forge must not execute forecast work that is no longer necessary merely because it once existed in the graph.

`MISSION_COMPLETION_IS_EVIDENCE_DERIVED = TRUE`
`INITIAL_ACTION_LIST_IS_NOT_COMPLETION_AUTHORITY = TRUE`

## Qualification sequence

Two separate real-world qualifications are required.

### Dynamic inner-loop canary

Input is one approved Mission, not a predeclared A/B script. Qualification proves:

```text
FORGE_DERIVES_ACTION_A = TRUE
ACTION_A_EXECUTED_BY_EP = TRUE
FORGE_RECONCILES_A_AND_REPLANS = TRUE
FORGE_DERIVES_SUCCESSOR_WITHOUT_OWNER_MESSAGE = TRUE
SUCCESSOR_MAY_DIFFER_FROM_INITIAL_FORECAST = TRUE
FORGE_CAN_INSERT_NEW_ACTION_AFTER_NEW_EVIDENCE = TRUE
MISSION_COMPLETION_DECIDED_FROM_EVIDENCE = TRUE
OWNER_IS_NOT_ACTION_MESSAGE_BUS = TRUE
```

### Cross-repository DAG canary

A later Mission spans at least two repositories and proves:

```text
FORGE_DERIVES_CROSS_REPO_DEPENDENCIES = TRUE
INDEPENDENT_REPOSITORIES_BECOME_CONCURRENTLY_ELIGIBLE = TRUE
DEPENDENT_ACTION_NEVER_EXECUTES_EARLY = TRUE
ARTIFACT_EVIDENCE_UNLOCKS_SUCCESSOR = TRUE
EP_RESOURCE_POLICY_REMAINS_SEPARATE_FROM_FORGE_PLAN = TRUE
MISSION_REPLANS_AFTER_PARALLEL_RESULTS = TRUE
```

The Execution Agent + Forge Platform installer role is a suitable real dogfood Mission for this second qualification once the required EP multi-execution/lease/capacity capabilities are qualified.